20 projects/fields have been identified that could contribute ~4.6BCFD within the decade

map of Nigeria
gas plant
Project #: 1
Project name: Ohaji South
Operator: Seplat Energy
Terrain: Onshore
Est BCFD: 0.3
First Gas date: 2024
Project phase: Final Investment Decision (FID) taken in 2024
gas plant
Project #: 2
Terrain: Onshore
Est BCFD: 0.2
First Gas date: 2028
Project phase: Opportunity pre-FID
gas plant
Project #: 3
Project name: Assa North
Operator: Shell Petroleum Development Company (SPDC)/Seplat Energy
Terrain: Onshore
Est BCFD: 0.2
First Gas date: 2025
Project phase: Final Investment Decision (FID) taken in 2018
gas plant
Project #: 4
Terrain: Onshore
Est BCFD: 0.1
First Gas date: 2028
Project phase: Opportunity pre-FID
gas plant
Project #: 5
Project name: Iseni
Operator: Shell Petroleum Development Company (SPDC)
Terrain: Onshore
Est BCFD: 0.1
First Gas date: 2027
Project phase: Final Investment Decision (FID) taken in 2024
gas plant
Project #: 6
Project name: Utapate
Operator: NNPCL Exploration and Production Ltd
Terrain: Onshore
Est BCFD: 0.4
First Gas date: 2024
Project phase: Development ongoing
gas plant
Project #: 7
Project name: Ubeta
Operator: TotalEnergies
Terrain: Onshore
Est BCFD: 0.3
First Gas date: 2027
Project phase: Final Investment Decision (FID) taken in 2024
gas plant
Project #: 8
Terrain: Onshore
Est BCFD: 0.1
First Gas date: 2025
Project phase: Opportunity pre-FID
gas plant
Project #: 9
Terrain: Shallow Water
Est BCFD: 0.3
First Gas date: 2027
Project phase: Opportunity pre-FID
gas plant
Project #: 10
Terrain: Shallow Water
Est BCFD: 0.2
First Gas date: 2028
Project phase: Opportunity pre-FID
gas plant
Project #: 11
Terrain: Shallow Water
Est BCFD: 0.04
First Gas date: 2030
Project phase: Opportunity pre-FID
gas plant
Project #: 12
Terrain: Shallow Water
Est BCFD: 0.4
First Gas date: 2027
Project phase: Development field
gas plant
Project #: 13
Terrain: Shallow Water
Est BCFD: 0.3
First Gas date: 2028
Project phase: Opportunity pre-FID
gas plant
Project #: 14
Terrain: Shallow Water
Est BCFD: 0.04
First Gas date: 2028
Project phase: Opportunity pre-FID
gas plant
Project #: 15
Project name: Akpo & Egina
Operator: TotalEnergies
Terrain: Deep Water
Est BCFD: 0.2
First Gas date: 2024
Project phase: Construction ongoing
gas plant
Project #: 16
Terrain: Deep Water
Est BCFD: 0.03
First Gas date: 2027
Project phase: Opportunity pre-FID
gas plant
Project #: 17
Terrain: Deep Water
Est BCFD: 0.3
First Gas date: 2030
Project phase: Development field
gas plant
Project #: 18
Terrain: Deep Water
Est BCFD: 0.1
First Gas date: 2030
Project phase: Opportunity pre-FID
gas plant
Project #: 19
Terrain: Deep Water
Est BCFD: 0.1
First Gas date: 2030
Project phase: Development field
gas plant
Project #: 20
Terrain: Deep Water
Est BCFD: 0.7
First Gas date: 2031
Project phase: Opportunity pre-FID
logo
The Decade of Gas initiative, launched in 2021, is focused on transforming Nigeria into a gas-powered economy by 2030 through series of policy reforms, gas supply projects maturation, gas infrastructure expansion, capacity building and robust investment attraction strategies.